01/06/2022
|
Case Action Form Closing Case with an effective date of 01/06/22 electronically filed by Ms. Mary E. Fischer on behalf of Megan J. Addison, Attorney Examiner, Public Utilities Commission of Ohio. |
01/07/2015
|
Notice of Withdrawal of Gregory L Williams from listed cases. |
02/03/2014
|
Service Notice for Supreme Court transmittal papers. |
02/03/2014
|
Supreme Court Transmittal Paper, SC No. 14-0008. |
01/03/2014
|
Notice of appeal of appellant of Allied Erecting & Dismantling Co., Inc filed by Timothy D. Berkebile Esq. (SC # 14-0008) |
12/11/2013
|
Report of Findings of Internal Review electronically filed by Ms. Carrie M. Dunn on behalf of Ohio Edison Company. |
11/06/2013
|
Service Notice |
11/06/2013
|
Entry on rehearing ordered, That the application for rehearing filed by Allied should be denied. It is, further, ordered, Allied's request for a stay of enforcement of the Commission's ordered is denied. |
10/21/2013
|
Memorandum Contra Application for Rehearing and Request for Special Order Staying Enforcement of the September 11, 2013 Order electronically filed by Mr. Gregory L. Williams on behalf of Ohio Edison Company. |
10/09/2013
|
Application For Rehearing And Request For Special Order Staying Enforcement electronically filed by Mr. Timothy D. Berkebile on behalf of Allied Erecting & Dismantling. |
09/11/2013
|
Service Notice |
09/11/2013
|
Opinion and Ordered, that, consistent with this Opinion and Order, OE conduct a internal review of its metering operations, practices, and policies. |
02/03/2012
|
Letter stating of a change of address and firm affiliation for Mark A. Whitt, Christopher T. Kennedy and Melissa L. Thompson for each of the above referenced cases filed by M. Whitt. |
12/09/2008
|
Notice of withdrawal of Jones Day as counsel for Ohio Edison Company filed by M. Whitt. |
05/30/2008
|
Post-hearing reply brief on behalf of complainant, Allied Erecting and Dismantling Co. Inc. filed by T. Berkebile. (original) |
05/29/2008
|
Post hearing reply brief on behalf of respondent, Ohio Edison Company, filed by G. Garber. |
05/29/2008
|
Post hearing reply brief on behalf of complainant Allied Erecting and Dismantling Co. Inc. filed by T. Berkebile. (FAX) |
05/19/2008
|
Post hearing brief of complainant Allied Erecting and Dismantling Company, Inc. filed by T. Grieco. (original) |
05/16/2008
|
Respondent Ohio Edison Company's post-hearing brief filed by M. Whitt. |
05/16/2008
|
Post hearing brief of complainant Allied Erecting and Dismantling Co. Inc. filed by F. Grieco. (FAX) |
05/01/2008
|
Transcript of hearing held on April 17, 2008, before K. Bojko, electronically filed by Mrs. Jennifer D. Duffer on behalf of Armstrong & Okey, Inc. |
04/30/2008
|
Transcript of hearing held April 16, 2008 before K. Bojko, electronically filed by Mrs. Jennifer D. Duffer on behalf of Armstrong & Okey, Inc. (Franklin County) |
04/14/2008
|
Motion In Limine and memorandum in support to exclude evidence regarding complainant's service history and Mahoning County Litigation filed on behalf of Ohio Edison Company by M. Whitt. |
04/14/2008
|
Motion to strike pre-filed testimony of Douglas Hull and memorandum in support filed on behalf of Ohio Edison Company by M. Whitt. |
04/14/2008
|
Exhibits continued. (Part 5 of 5) |
04/14/2008
|
Exhibits continued. (Part 4 of 5) |
04/14/2008
|
Exhibits continued. (Part 3 of 5) |
04/14/2008
|
Exhibits continued. (Part 2 of 5) |
04/14/2008
|
Notice of filing hearing exhibits filed on behalf of Allied Erecting & Dismantling Company by T. Grieco. (Part 1 of 5) |
04/14/2008
|
Notice of filing deposition transcripts of Karen Dewey, William Giese, John W. Morgan, Lisa Nentwick, and John Zitkovich filed on behalf of Allied Erecting & Dismantling Co., Inc. by T. Berkebile. |
04/14/2008
|
Motion for leave to file deposition of Douglas Hull and memorandum in support filed on behalf of Ohio Edison Company by M. Rawlin. |
04/10/2008
|
Deposition of John Ramun filed by G. Garber on behalf of the Ohio Edison Company. |
04/10/2008
|
Deposition of Jay Collins filed by G. Garber on behalf of the Ohio Edison Company. |
04/10/2008
|
Deposition of James Smith filed by G. Garber on behalf of Ohio Edison Company. |
04/10/2008
|
Notice of filing depositions of John Ramun, Jay Collins and Jim Smith filed by G. Garber on behalf of Ohio Edison Company. |
04/02/2008
|
Direct testimony of Lisa K. Nentwick on behalf of respondent, Respondent's Exhibit 1. |
04/02/2008
|
Notice of appearance filed on behalf of the Ohio Edison Company by M. Rawlin. |
04/02/2008
|
Witness list of respondent Ohio Edison filed by M Rawlin. |
04/02/2008
|
Complaint's witness list filed by F. Grieco on behalf of Allied Erecting & Dismantling Co., Inc. |
04/02/2008
|
Expert testimony of Douglas Hull filed by F. Grieco on behalf of the complainant. |
03/31/2008
|
Respondent's opposition to complainant's motion to compel discovery of redacted material filed on behalf of Ohio Edison Company by G. Garber. |
03/18/2008
|
Motion to compel discovery of redacted material and memorandum in support filed on behalf of Allied Erecting & Dismantling Co. Inc., by T. Grieco. |
02/11/2008
|
Entry ordering that this case be scheduled for a hearing on April 16, 2008, at 10:00 a.m., in hearing room 11-F at the Commission offices, 180 East Broad Street, 11th floor, Columbus, Ohio 43215-3793; that as agreed upon by the parties, all expert testimony and each party's witness list shall be filed with the Commission no later than April 2, 2008 and a prehearing conference shall be scheduled for 10;00 a.m., on April 2, 2008 in hearing room 11-F at the Commission offices. (KWB) |
02/11/2008
|
Service Notice |
09/25/2007
|
Motion for admission pro hac vice of Christopher R. Opalinski, F. Timothy Grieco and Timothy D. Berkebile filed by J. Skolnick on behalf of Allied Erecting & Dismantling Co., Inc. |
09/20/2007
|
Entry ordering that a settlement conference be scheduled at 10:00 a. m. on Wednesday, October 24, 2007, in hearing room 11-F, on the 11th floor of the Commission's offices, 180 East Broad Street, Columbus, Ohio 43215. (KB) |
09/20/2007
|
Service Notice |
09/04/2007
|
Answer filed on behalf of Ohio Edison Company by M. Whitt. |
08/13/2007
|
Complaint service letter and copy of complaint mailed to Leila Vespoli, Ohio Edison Company. |
08/13/2007
|
Complaint response letter and copy of brochure mailed to Allied Erecting & Dismantling, complainant. |
08/10/2007
|
In the matter of the complaint of Allied Erecting & Dismantling vs Ohio Edison Company for alleged excessive billing practices. |