CASE NUMBER: 06-0967-EL-BLN
CASE DESCRIPTION: FIRSTENERGY CORPORATION/ST. LUKE HOSPITAL
DOCUMENT SIGNED ON: 4/25/2024
DATE OF SERVICE: ________________________________________
02/09/2007 Letter advising that construction on project was completed on approximately January 30, 2007 and the work on the associated substation and minor work on local distributing circuits is continuing and is expected to be completed shortly, filed on behalf of FirstEnergy Service Company by T. Krauss.
11/15/2006 Letter of notification stating construction on Angola-Midway project 138kV transmission line tap to St. Luke's Hospital substation project will start on November 13, 2006, instead of November 1, 2006 filed by T. Krauss on behalf of FirstEnergy Service Company.
09/06/2006 Staff investigation report and recommendation.
07/31/2006 In the matter of the letter of notification of American Transmission Systems, Inc. and The Toledo Edison Company proposing the Angola-Midway 138kV transmission line tap to St. Luke's Hospital substation.