04/04/2007
|
Letter notifying the Commission that the project was completed on March 7, 2007 filed by S. Lane on behalf of Duke Energy. |
03/23/2006
|
Staff Investigation Report and Recommendation, filed by PUCO staff. |
03/01/2006
|
Letter stating that the Phase 1 Archaeological Survey for the Cincinnati Gas and Electric Company's Maineville 138kV Transmission Line Loop has been submitted under separate cover, filed by S. Lane. |
02/17/2006
|
In the matter of the Letter of Notification for Maineville 138 kv Electric Transmission Line, Loop regarding a Cincinnati Gas and Electric Company project. |
|