02/15/2007
|
Letter stating the project was completed and put in service on September 22, 2006, filed by P. Robertson on behalf of Dayton Power and Light Company. |
02/15/2007
|
Letter stating project was completed and was put in service on September 22, 2006, filed by P. Robertson on behalf The Dayton Power and Light Company. (original) |
04/28/2006
|
Letter of Notification to the Ohio Power Siting Board that The Dayton Power and Light Company is starting construction on the Eldean-Sidney 138 k V transmission Line Tap for Millcreek Substation on Monday, May 1, 2006, filed by P. Robertson, P.E. on behalf of The Dayton Power and Light Company. |
03/29/2006
|
Staff investigation report and recommendation filed by PUCO staff. |
03/27/2006
|
Motion and memorandum in support for waiver of notice requirements for Letter of Notification, filed on behalf of the Dayton Power and Light Company by E. Rizer. |
02/17/2006
|
In the matter of the letter of notification of the Dayton Power and Light Company for the Eldean-Sidney 138 kV Line Tap for Millcreek Substation. |