CASE NUMBER: 06-0295-EL-BLN
CASE DESCRIPTION: AMERICAN TRANSMISSION SYSTEMS INCORPORATED/JACKMAN-VULCAN#2 138kV/TOLEDO HOSPITAL SUBSTATION
DOCUMENT SIGNED ON: 9/29/2020
DATE OF SERVICE: ________________________________________
10/13/2006 Letter of notification that construction on Jackman-Vulcan #2 138 kV Transmission Line Loop to Toledo hospital substation was completed on September 27, 2006, filed by T. Krauss on behalf of FirstEnergy Service Company.
06/12/2006 Letter stating that construction began on May 26, 2006 and the Commission will be notified once the project is complete filed by T. Krauss on behalf of FirstEnergy Service Company.
03/20/2006 Staff investigation report and recommendation, filed by PUCO staff.
02/09/2006 In the matter of the application of American Transmission Systems, Incorporated proposing to extend ATST's existing Jackman-Vulcan #2 138 KV transmission line approximately 0.3 miles to a new substation being constructed at the Toledo Hospital.