DIS - Case Record for 05-1578-RR-FED Skip to main content

Case Record For:

05-1578-RR-FED

Case Title: INDIANA & OHIO RAILWAY; NORFOLK SOUTHERN RAILWAY; CSX TRANSPORTATION;WHEELING & LAKE ERIE RAILWAY
Status: AR-Archived
Industry Code: RR-RAILROAD
Purpose Code: FED-Federally funded warning projects
Date Opened: 12/23/2005
Date Closed: 3/19/2007
Printable Docket Card Service List
View All
1 - 9 of 9 documents 1 /  1 
Date FiledSummaryPages
03/19/2007Memo automatically closing case with an effective date of 3/19/2007.1
01/03/2007Entry ordered; that NS's request for an extension of time to complete the project be granted; that NS complete the above-identified project no later than March 4, 2007.2
01/03/2007Service Notice4
12/22/2006Memo recommending that the Commission approve request for extension of time to complete a grade crossing project in Erie County, filed by PUCO staff-Railroad Section.2
12/21/2006Request for extension of construction deadline and memorandum filed on behalf of Indiana & Ohio Railway , Norfolk Southern Railway, CSX Transportation, and Wheeling & Lake Erie Railway Company by D. Casey-Talbott.5
03/23/2006Detailed cost estimate, material list and engineering plans for crossing, filed on behalf of Norfolk Southern Corporation by B. Sykes.26
01/05/2006Service Notice5
01/04/2006Entry ordered; that I&O, CSX, NS, and W&LE submit to the Commission and ORDC site plans and cost estimates for the projects by April 4, 2006, that by April 11, 2006 each file a letter in this docket advising that it has submitted site plans and cost estimates to the Commission and ORDC; that following approval of site plans and cost estimates by ORDC, I&O, CSX, NS, and W&LE proceed with construction of the projects with construction to be completed by January 4, 2007, that I&O, CSX, NS, and W&LE follow the detailed instructions as outlined in the ORDC letter of construction authorization, that I&O, CSX, NS, and W&LE notify the Commission and ORDC 30 days before the projected date of completion; that, at that time staff or ORDC makes its final inspection and if its finds that the installations are completed and have been put in service, staff will file a memorandum in this docket directing the docketing division close this case of record.4
12/23/2005In the matter of the authorization of the Indiana & Ohio Railway, Norfolk Southern Railway, CSX Transportation, and Wheeling & Lake Erie Railway to install warning devices at 11 grade crossings.9
 
1 /  1 
      
      
Attorney General:
Attorney Examiner: