03/30/2009
|
Letter in response to the notification that the estimated start time was to occur on March 27, 2006. The actual start of construction on the project was delayed until March 4, 2008, filed by T. Krauss on behalf of FirstEnergy Service Company. |
03/30/2009
|
Letter of notification and construction notice of construction status update filed by T. Krauss on behalf of FirstEnergy. |
01/30/2006
|
Staff Investigation Report and Recommendation filed on behalf of PUCO staff. |
12/22/2005
|
In the matter of the application of the letter of notification Bay Shore-Jeep No. 2, and Bay Shore-Ironville 138kV Transmission Lines-Replace Structure No. 288 located Southwest of Millard Ave. and Otter Creek Rd. |