10/10/2006
|
Letter stating that Bixby-Shannon 138-kV Line Reconductor Project is completed filed by S. Williams on behalf of American Electric Power Service Corporation. |
09/29/2005
|
Letter stating that work on the Bixby-Shannon 138kV Line Reconductor Project is scheduled to begin on or about October 3, 2005 filed by S. Williams in behalf of AEP. |
08/26/2005
|
Staff investigation report and recommendation filed by PUCO Staff. |
08/03/2005
|
In the matter of the construction notice for the Bixby - Shannon 138kV line, reconductor project. |