01/31/2006
|
Letter notify PUCO staff that project was completed on January 12, 2006, filed on behalf of FirstEnergy Service Company by T. Krauss. |
08/18/2005
|
Letter stating that they are planning to begin the installation work on August 22, 2005 filed by T. Krauss on behalf of FirstEnergy |
07/27/2005
|
Response to the Letter of Notification filed on April 21, 2005 and additionally May 25, 2005 letter indicating a proposed July 23, 2005 start of construction date, construction is expected to begin on August 1, 2005, filed on behalf of FirstEnergy Service Company by T. Krauss. |
05/27/2005
|
Correction to Letter of Notification filed April 21, 2005, filed on behalf of applicant by T. Krauss. |
05/25/2005
|
Staff Investigation Report and Recommendations, filed by PUCO staff J. O'Dell. |
04/21/2005
|
In the matter of the letter of notification of The Cleveland Electric Illuminating Company for the Harding Group #12 and #14 138kV transmission line circuit for the Charter Steel Mill Substation Project. |
|