CASE NUMBER: 05-0539-EL-BLN
CASE DESCRIPTION: CEI/CHARTER STEEL MILL SUBSTATION
DOCUMENT SIGNED ON: 4/25/2024
DATE OF SERVICE: ________________________________________
01/31/2006 Letter notify PUCO staff that project was completed on January 12, 2006, filed on behalf of FirstEnergy Service Company by T. Krauss.
08/18/2005 Letter stating that they are planning to begin the installation work on August 22, 2005 filed by T. Krauss on behalf of FirstEnergy
07/27/2005 Response to the Letter of Notification filed on April 21, 2005 and additionally May 25, 2005 letter indicating a proposed July 23, 2005 start of construction date, construction is expected to begin on August 1, 2005, filed on behalf of FirstEnergy Service Company by T. Krauss.
05/27/2005 Correction to Letter of Notification filed April 21, 2005, filed on behalf of applicant by T. Krauss.
05/25/2005 Staff Investigation Report and Recommendations, filed by PUCO staff J. O'Dell.
04/21/2005 In the matter of the letter of notification of The Cleveland Electric Illuminating Company for the Harding Group #12 and #14 138kV transmission line circuit for the Charter Steel Mill Substation Project.