CASE NUMBER: 05-0508-EL-BNR
CASE DESCRIPTION: THE CINCINNATI GAS AND ELECTRIC COMPANY
DOCUMENT SIGNED ON: 4/24/2024
DATE OF SERVICE: ________________________________________
12/16/2005 Letter of notification that the CG&E Port Union to Hall Reconductor Project-Feeder Circuit 3885 138kV Transmission Line was completed on November 30, 2005, filed on behalf of applicant by S. Lane.
08/25/2005 Pre-construction notification letter stating construction will begin on September 1, 2005, filed by S. Lane on behalf of Cinergy.
05/06/2005 Staff Investigation Report and Recommendation for the Port Union-Hall Reconductor Project.
04/14/2005 In the matter of the construction notice regarding a CG&E Co. project Port Union to Hall Reconductor Project Feeder Circuit 3885-138kV Transmission Line.