12/27/2001
|
Letter stating that the construction project has been completed filed by J. Heppner. |
04/12/2001
|
Letter of Notification; construction is scheduled to start on 4/16/01 filed by J. Heppner on behalf of AEP. |
12/08/2000
|
Investigation report approving the Letter of Notification, filed by J. O'Dell, PUCO staff. |
12/07/2000
|
Response to Letter of Notification filed by K. Lambeck, PUCO staff. |
10/23/2000
|
ICN #0002 Additional information filed on behalf of appli- cant by J. Heppner. (2 pgs.) |
10/11/2000
|
ICN #0001 In the matter of the Letter of Notification of Ohio Power Company for the East Lima-Sorenson 345 kV Line, Service to National Power Cooperative, Inc.'s Robert P. Mone Plant. (19 pgs.) |