CASE NUMBER: 00-1038-RR-FED
CASE DESCRIPTION: FEDERAL GRADE CROSSING/2000
DOCUMENT SIGNED ON: 4/23/2024
DATE OF SERVICE: ________________________________________
05/09/2002 Entry closing this case of record.
03/21/2002 Memo filed by G. Martin, PUCO staff, requesting that these cases be closed of record.
09/19/2001 Service Notice
09/18/2001 Memo filed by G. Martin, PUCO staff, with attached request from the Indiana & Ohio Rail System for a further extension of 30 days within which to complete the project.
09/18/2001 Entry ordering that I&O be granted its requested extension as delineated in Finding 4. (AE)
08/17/2001 Service Notice.
08/16/2001 Entry ordering that NS be granted the extensions as delineated in Finding 4; that the project should be completed by September 20, 2001. (AE)
08/15/2001 Memo recommending that NS be granted a 30-day extension of time, until September 20, 2001, within which to complete the active warning device projects, filed by L. Dalton, PUCO staff.
07/20/2001 Entry ordering that NS be granted extensions as delineated in Findings 4 and 5. (AE)
07/19/2001 Memo filed by L. Dalton, PUCO staff, stating that Norfolk Southern is requesting an extension of time in which to comply with the Commission order issued in this case (for Holmes County).
07/19/2001 Memo filed by L. Dalton, PUCO staff, stating that Norfolk Southern is requesting an extension of time in which to comply with the Commission order issued in this case (for Portage County).
06/22/2001 Service Notice
06/21/2001 Entry ordering that construction deadlines for the installation of active warning devices be extended to September 18, 2001 in Case No. 00-1038-RR-FED and January 17, 2002 in Case No. 00-1794-RR-STP.
06/01/2001 Memo, with attached request from Railroad, stating that the deadline for this project should be extended 60 days, filed on behalf of the PUCO staff by B. Johrendt.
07/20/2000 Entry ordering that CSX, Indiana & Ohio, NOWR, and Norfolk Southern submit to the Commission site plans and cost estimates mates for the projects within 90 days of this entry; that CSX, Indiana & Ohio, NOWR, and Norfolk Southern proceed with construction of the projects, with construction to be completed by July 20, 2001; that CSX, Indiana & Ohio, NOWR, and Norfolk Southern notify the Commission's railroad section upon completion of each project, at which times Commission staff will make its final inspection. (4 pgs.)
07/20/2000 Entry ordering that CSX, Indiana & Ohio, NOWR, and Norfolk Southern submit to the Commission site plans and cost esti- mates for the projects within 90 days of this entry; that CSX, Indiana & Ohio, NOWR, and Norfolk Southern proceed with construction of the projects, with construction to be com- pleted by July 20, 2001; that CSX, Indiana & Ohio, NOWR, and Norfolk Southern notify the Commission's railroad section upon completion of each project, at which times Commission staff will make its final inspection. (4 pgs.)
06/30/2000 Memo filed by J. Reinhardt, PUCO staff, stating that the Ohio Rail Development Commission has authorized construction for the railroad-highway grade crossing warning projects listed in the memo.
06/30/2000 Memo filed by J. Reinhardt, PUCO staff, stating that the Ohio Rail Development Commission has authorized construc- tion for the railroad-highway grade crossing warning pro- jects listed in the memo. (2 pgs.)
06/09/2000 In the matter of the Federal Grade Crossing Warning Project for the Year 2000. (1 pg.)