Date Filed | Summary | Pages |
04/11/1994 | ICN #0005 Letter stating that construction was completed on March 30, 1994, filed on behalf of applicant by G. Cunningham. | 0 |
12/22/1993 | ICN #0004 Letter stating that construction is scheduled to begin on January 3, 1994, filed on behalf of applicant by T. Burgess. | 0 |
10/05/1993 | ICN #0003 Response to Letter of Notification, filed by K. Wissman, OPSB staff. | 0 |
09/23/1993 | ICN #0002 Investigation report approving letter of notifi- cation, filed by J. O'Dell, PUCO staff. | 0 |
09/09/1993 | ICN #0001 In the matter of the application of Ohio Edison Company for a board letter of notification for the proposed construction of two new one-pole, single circuit corner dead-end structures on the centerline of the Chamberlin- Darrow 138 kV #298 transmission line, loop to Hudson Village. | 0 |
|