Date Filed | Summary | Pages |
10/02/1997 | Entry ordering that this case be closed of record. (2 pgs.) | 2 |
09/17/1997 | Final notification letter submitted by Conrail, filed by B. Johrendt, PUCO staff. (3 pgs.) | 3 |
06/03/1993 | Entry approving the site plans and cost estimates and ordering that Conrail proceed with the installation of the corridor project in Springfield, Ohio, to be com- pleted by 11/30/95; that Conrail notify the Commission's railroad section upon completion of each installation and railroad crossing closure. | 0 |
05/12/1993 | Memo from George Stanforth, ODOT, authorizing the Con- solidated Rail Corp. to proceed with the construction of the Clark County, City of Springfield, various routes, AAR No. Various, filed by B. Johrendt, PUCO staff. | 0 |
09/22/1992 | Plans and estimates filed on behalf of Conrail by B. Johrendt. | 0 |
08/06/1992 | Entry granting Consolidated Rail Corp. an extension of time until 9/8/92 to submit cost estimates and site plans. | 0 |
07/13/1992 | Copy of letter from J.D. Cossel, Conrail, requesting an extension of time to submit the plans and estimates, filed by the PUCO staff by J. Reinhardt. | 0 |
04/16/1992 | Entry adopting the Agreement and Recommendation; the Commission will pay the public share of the project costs; and ordering Consolidated Rail submit for Commission approval site plans and cost estimates for the project within 90 days. | 0 |
04/03/1992 | In the matter of the request for a Corridor Project, with the installation of flashing lights and gates, new surfaces and crossing closures to vehicles of Consolidated Rail Corp. at various locations in the City of Springfield, Clark County. | 0 |