Date Filed | Summary | Pages |
10/08/1993 | Memo closing case with effective date of 10/8/93. | 0 |
01/11/1991 | ICN #0004 Letter stating that the planned date of construction is January 9, 1991, filed on behalf of applicant by T. Burgess. | 0 |
06/20/1990 | ICN #0003 Response letter to the Letter of Notification filed on behalf of the OPSB by J. Lehr Kennedy. | 0 |
06/20/1990 | ICN #0002 Memo to OPSB recommending that the Letter of Notification filed by Ohio Edison qualify for the Letter of Notification process with conditions. | 0 |
05/21/1990 | ICN #0001 Letter of Notification to construct 0.3 miles of new transmission line into the new Leaside Substation filed on behalf of Ohio Edison Company. | 0 |