Date Filed | Summary | Pages |
07/11/2024 | Notice that Projects are Completed and In-Service electronically filed by Miss Pamela Archer on behalf of The Dayton Power and Light Company d/b/a AES Ohio. | 2 |
09/19/2023 | Notice of Proof of Compliance with Notification Requirements electronically filed by Mr. Christopher C. Hollon on behalf of The Dayton Power and Light Company d/b/a AES Ohio. | 4 |
09/05/2023 | Staff Report of Investigation electronically filed by Robert A. Holderbaum on behalf of PUCO Staff. | 8 |
06/29/2023 | Notification of OHPO Coordination Approval for Sidney-Franklin 138kV Transmission Line Adjustment Project electronically filed by Ms. Sarah Howdeshelt on behalf of Dayton Power & Light Company d/b/a AES Ohio. | 5 |
06/21/2023 | Notice of Compliance with notification requirements for the Sidney – Franklin 138kV Transmission Line Adjustment Project electronically filed by Mr. Christopher C. Hollon on behalf of The Dayton Power and Light Company d/b/a AES Ohio. | 21 |
06/14/2023 | Construction Notice Application for the Sidney-Franklin 138kV Transmission Line Adjustment Project electronically filed by Ms. Sarah Howdeshelt on behalf of Dayton Power & Light Company d/b/a AES Ohio. | 133 |
06/09/2023 | In the Matter of the Pre-Application Notification Letter, Construction Notice Application of AES Ohio for a Certificate of Environmental Compatibility and Public Need for the Sidney – Franklin 138kV Transmission Line Adjustment Project
electronically filed by Ms. Sarah Howdeshelt on behalf of Dayton Power & Light Company d/b/a AES Ohio. | 2 |