Date Filed | Summary | Pages |
03/01/2024 | Notice of Proof of Compliance, Landowner Notification electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 2 |
02/26/2024 | Notification of Start of Construction electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 2 |
02/09/2024 | Service Notice / Staff Report. | 1 |
02/09/2024 | Staff Report of Investigation electronically filed by Mark C. Bellamy on behalf of OPSB Staff. | 7 |
01/03/2024 | Response to OPSB Staff's 1st Data Request electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 7 |
11/21/2023 | Construction Notice Application for the Marysville-Cadence Solar 345 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 321 |
11/21/2023 | Notice of Correction to November 6, 2023 Application Filing electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 4 |
11/06/2023 | In the Matter of the Pre-Application Notification Letter electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company. | 2 |