Date Filed | Summary | Pages |
01/12/2023 | Notification of Completion of Construction and In-Service Date electronically filed by Mrs. Tammy M. Meyer on behalf of Duke Energy Ohio Inc. and D'Ascenzo, Rocco and Kingery, Jeanne and Akhbari, Elyse Hanson and Vaysman, Larisa. | 2 |
10/06/2022 | Letter Accepting Staff's Conditions electronically filed by Mrs. Tammy M. Meyer on behalf of Duke Energy Ohio Inc. and D'Ascenzo, Rocco and Kingery, Jeanne. | 2 |
09/30/2022 | Service Notice (Staff Report). | 3 |
09/30/2022 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 6 |
09/22/2022 | Proof of Service for Duke Energy Ohio, Inc. Finneytown Transmission Pole Project electronically filed by Mrs. Tammy M. Meyer on behalf of Duke Energy Ohio Inc. and D'Ascenzo, Rocco and Kingery, Jeanne and Akhbari, Elyse Hanson and Vaysman, Larisa. | 7 |
09/15/2022 | Duke Energy Ohio, Inc. submits revisions to filing electronically filed by Mrs. Debbie L. Gates on behalf of Duke Energy Ohio Inc. and D'Ascenzo, Rocco O. Mr. and Akhbari, Elyse and Vaysman, Larisa and Kingery, Jeanne W. | 2 |
09/15/2022 | Construction Notice Application for the Finneytown Transmission Pole Project submitted by Duke Energy Ohio, Inc. electronically filed by Mrs. Debbie L. Gates on behalf of Duke Energy Ohio Inc. and D'Ascenzo, Rocco O. Mr. and Akhbari, Elyse and Kingery, Jeanne W and Vaysman, Larisa. | 25 |
09/09/2022 | In the Matter of the Pre-Application Notification Letter electronically filed by Mrs. Debbie L. Gates on behalf of Duke Energy Ohio Inc., D'Ascenzo, Rocco O. Mr., Vaysman, Larisa, Kingery, Jeanne W., and Akhbari, Elyse. | 2 |
|