08/23/2023 | Notification of In-Service Date for the Cartwright 138 kV Switch Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
02/02/2023 | Notice of Proof of Compliance with Condition 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 152 |
10/12/2022 | Notice of Updated Start of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
10/05/2022 | Notice of Start of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
02/18/2022 | Service Notice - Staff Report. | 2 |
02/18/2022 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 6 |
01/28/2022 | Notice of Adjustment electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 3 |
11/29/2021 | In the Matter of the Construction Notice for the Cartwright 138kV Switch Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 82 |