09/18/2024 | Notice of Certificate Compliance with Condition 2 – Phase 2 Balance of System Preconstruction Conference Agenda – Updated Date electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 3 |
09/18/2024 | Notice of Certificate Compliance with Condition 12 – NPDES and Driveway Permits electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 2 |
09/18/2024 | Notice of Certificate Compliance with Condition 2 – Phase 2 Balance of System Preconstruction Conference Agenda electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 3 |
08/30/2024 | Notice of Certificate Compliance Condition 4 – Balance of System Engineering Drawings electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 3 |
08/30/2024 | Notice of Certificate Compliance with Condition 26 – Phase 1 Stormwater Pollution Prevention Plan electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 543 |
08/30/2024 | Notice of Certificate Compliance Condition 9 – Emergency Response Plan electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 36 |
08/30/2024 | Notice of Certificate Compliance Condition 31 – Updated Decommissioning Plan electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 18 |
08/29/2024 | Notice of Compliance with Condition 14 Phase 1 Complaint Resolution Plan and Notice electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 9 |
08/27/2024 | Notice of Certificate Compliance Condition 1 – Phase 1 Spill Prevention Control and Countermeasure Plan electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 4 |
08/23/2024 | Notice of Certificate Compliance with Condition 21 - Sound Level Assessment Report for Phase 1 Construction of Switchyard electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 67 |
08/22/2024 | Notice of Certificate Compliance with Condition 2 – Phase 1 Interconnection Switchyard Preconstruction Conference Agenda electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 4 |
08/13/2024 | Notice of Certificate Compliance with Condition 11 – Switchyard Construction Start Date – October 1, 2024 electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 4 |
08/09/2024 | Notice of Certificate Compliance Condition 17 – Memorandum of Understanding
with the State Historic Preservation Office electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 36 |
07/29/2024 | Notice of Proof of Compliance for Condition 9 – Emergency Response Plan electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 35 |
07/29/2024 | Notice of Proof of Compliance with Condition 4 – Point of Interconnection Switchyard Engineering Drawings electronically filed by Christine M.T. Pirik on behalf of Marion County Solar Project, LLC. | 3 |