Date Filed | Summary | Pages |
11/06/2020 | Notice of completion of the Adjustment to Heppner-Rhodes 138 kV Transmission Line Rebuild Project as of December 27, 2019 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 2 |
08/21/2019 | Notice of Construction Start Date electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 2 |
06/25/2018 | Acceptance of Staff Condition electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 2 |
06/22/2018 | Service Notice (OPSB) | 2 |
06/22/2018 | Staff Report of Investigation electronically filed by Adam Bargar on behalf of Staff of OPSB. | 5 |
06/19/2018 | Notification - Supplemental to Proof of Compliance filed 6/6/2018 electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 17 |
06/06/2018 | Notification (Proof of Compliance with O.A.C. 4906-6-07 and 4906-6-08) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 9 |
05/31/2018 | Letter of Notification electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 206 |
05/24/2018 | In the matter of the Pre-Application Notification Letter electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 2 |