Case Title: East Lima-Marysville 345kV Transmission Line Extension Project
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 2/9/2018
Date Closed:
Printable Docket Card Service List
View All
1 - 5 of 5 documents 1 /  1 
Date FiledSummaryPages
08/28/2019Notice of Completion of Construction electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.2
05/09/2018Notification stating that construction commenced on March 27, 2018 electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.2
03/19/2018Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.4
03/02/2018Construction Notice Application electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.84
02/09/2018In the matter of the (Pre-Application Notification Letter) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.3
 