Date Filed | Summary | Pages |
11/04/2019 | Notice stating that construction on Project was completed on June 1, 2018 filed by N. Bryksenkova on behalf of FirstEnergy Service Company. | 1 |
04/09/2018 | In the matter of the letter of Notification of the Clark-Greene 138 kV and Clark-East Springfield 138 kV Transmission Lines Rebuild Project to advised
that construction on this Project, which was recommended for automatic approval on April 5, 2018 in the Staffs Report of Investigation docketed on March 29, 2018 commenced on April 6, 2018. We will notify you once the Project has been completed filed by Nataliya Bryksenkova on behalf of FirstEnergy Service Company. | 1 |
03/29/2018 | Service Notice. | 2 |
03/29/2018 | Staff Report of Investigation electronically filed by Adam Bargar on behalf of Staff of OPSB. | 4 |
03/16/2018 | Proof of Pub of Public Notice of Filing of Letter of Notification Application electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. (Clark County) | 4 |
03/07/2018 | Letter of Notification Application for a Certificate of Environmental Compatibility and Public Need (Part 10 of 10) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 22 |
03/07/2018 | Letter of Notification Application for a Certificate of Environmental Compatibility and Public Need (Part 9 of 10) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 13 |
03/07/2018 | Letter of Notification Application for a Certificate of Environmental Compatibility and Public Need (Part 8 of 10) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 14 |
03/07/2018 | Letter of Notification Application for a Certificate of Environmental Compatibility and Public Need (Part 7 of 10) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 121 |
03/07/2018 | Letter of Notification Application for a Certificate of Environmental Compatibility and Public Need (Part 6 of 10) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 20 |
03/07/2018 | Letter of Notification Application for a Certificate of Environmental Compatibility and Public Need (Part 5 of 10) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 9 |
03/07/2018 | Letter of Notification Application for a Certificate of Environmental Compatibility and Public Need (Part 4 of 10) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 11 |
03/07/2018 | Letter of Notification Application for a Certificate of Environmental Compatibility and Public Need (Part 3 of 10) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 23 |
03/07/2018 | Letter of Notification Application for a Certificate of Environmental Compatibility and Public Need (Part 2 of 10) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 43 |
03/07/2018 | Letter of Notification Application for a Certificate of Environmental Compatibility and Public Need (Part 1 of 10) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 27 |