01/27/2017 | Correspondence Start of Construction electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield. | 2 |
01/27/2017 | Correspondence of Dominion East Ohio in Compliance with Staff Report Condition No. 1 electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield. | 14 |
01/11/2017 | Notice of Dominion East Ohio of the Start of Construction electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield. | 2 |
01/10/2017 | Correspondence of Dominion East Ohio Gas in Compliance with Staff Report Condition No. 4 - Frac-Out Plan electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield. | 11 |
01/10/2017 | Correspondence of Dominion East Ohio Gas in Compliance with Staff Report Condition No. 3 electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield. | 4 |
01/10/2017 | Dominion East Ohio's Supplement to its Letter of Notification electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield. | 3 |
01/06/2017 | Service Notice for Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
01/06/2017 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB | 8 |
12/01/2016 | Letter of notification of Dominion East Ohio Submitting Construction Plans - Part 2 electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield | 16 |
12/01/2016 | Letter of notification of Dominion East Ohio Submitting Construction Plans - Part 1 electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield. | 26 |
12/01/2016 | Dominion East Ohio Proof of Service electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield. | 6 |
11/30/2016 | Proof of Pub of Dominion East Ohio electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield. | 6 |
11/21/2016 | Correspondence of Dominion East Ohio Waiving Expedited Treatment Period electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield. | 2 |
11/14/2016 | Dominion East Ohio Proof of Payment electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield. | 4 |
11/14/2016 | Letter of Notification Application of Dominion East Ohio for LEC-Clean Energy Power Plant Installation Project, Part 10 electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield. | 93 |