Date Filed | Summary | Pages |
08/09/2019 | Case Action Form Close Cases as of 8/9/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio. | 2 |
02/21/2017 | Notification of In-Service Date for the Yager-Azalea 138 kV Transmission Line Project
electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. | 2 |
02/16/2016 | Letter of Notification re Construction Start Date electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
02/02/2016 | Correspondence Accepting Staff's Conditions electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
01/28/2016 | Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB. | 6 |
01/27/2016 | Correspondence re Supplemental Information electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 3 |
11/20/2015 | Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 5 |
11/05/2015 | Letter of Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company | 38 |
11/05/2015 | Letter of Notification -Part 2 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 38 |
11/05/2015 | In the matter of the Letter of Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 12 |