07/17/2015 | Notice of Withdrawal and Substitution of Counsel electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. | 3 |
07/10/2015 | Letter of Notification for Don Marquis-Bixby 345 kV Transmission Line Prop Structure electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. | 2 |
09/25/2014 | Proof of Pub Don Marquis-Bixby 345 kV Transmission Line Prop Structure Project in the Chillicothe Gazette 9/1/2014 electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company | 4 |
09/16/2014 | Staff Report of Investigation electronically filed by Mrs. Yvonne W. Cooper on behalf of Staff of OPSB. | 4 |
08/26/2014 | In the matter of the Letter of Notification for the Don Marquis-Bixby 345 Kv Transmission Line
Prop Structure Project electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 20 |