Date Filed | Summary | Pages |
07/06/2015 | Letter of Notification for the Chamberlin-West Akron 138 kV Transmission Line Tap to Sourek Substation Project filed on behalf of FirstEnergy by J. Thacker. | 1 |
01/22/2015 | Proof of publication in The Akron Beacon Journal for Notice of Proposed Major Utility Facility filed on behalf of American Transmission Systems, Inc. by R. Schmidt, Jr. | 3 |
10/23/2014 | Response to the Letter of Notification informing that construction will begin on October 27, 2014 and will notify once completed filed by J. Thacker on behalf of FirstEnergy Service Company. | 1 |
10/21/2014 | Letter of Notification providing supplemental information of the project to the Board filed by J. Thacker on behalf of First Energy. | 3 |
09/17/2014 | Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB | 3 |
08/29/2014 | Request for expedited review filed by J. Toth on behalf of FirstEnergy Service Company. | 1 |
08/29/2014 | In the matter of the Letter of Notification Chamberlin-West Akron 138kV Transmission Line Tap to Sourek Substation Project. | 21 |