Date Filed | Summary | Pages |
02/16/2017 | Letter of Notification that the Lyons-East Fayette portion of this project was completed on February 13, 2017. | 1 |
08/11/2016 | Correspondence serving as notice from American Transmission Systems, Incorporated ("ATSI") of Supplemental Information of
the continuation of construction for the Lyons to East Fayette portion of the above referenced Project filed by N. Bryksenkova, Engineer on behalf of FirstEnergy Service Company. | 1 |
07/13/2015 | Letter of notification that the Allen Junction-East Fayette was completed on December 30, 2014 filed by J. Thacker. | 1 |
11/24/2014 | Correspondence Supplemental Information Letter electronically filed by Ms. Jessica L Thacker on behalf of FirstEnergy Service Company | 2 |
10/09/2014 | Supplemental information to the Board concerning the construction of the Allen Junction-East Fayette Transmission Line Project filed by J. Thacker, on behalf of FirstEnergy Service Company. | 2 |
09/11/2014 | Letter of notification stating that the Allen Junction-East Fayette 138 kV Transmission Line Rebuild Project will begin on September 12, 2014 filed by J. Thacker on behalf of FirstEnergy Service Company. | 1 |
08/11/2014 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 3 |
08/01/2014 | Proof of Publication filed (Lucas & Fulton Counties) | 5 |
07/18/2014 | In the matter of the Letter of Notification of Allen Junction-East Fayette 138 kV Transmission Line Rebuild Project. | 68 |