Date Filed | Summary | Pages |
10/30/2014 | Correspondence stating that project construction is complete electronically filed by Mrs. Kim D Carter on behalf of Wilson, Sean Mr. and Green, Steven Mr. and Leoni, Andrew Mr. and Melland, Kathleen Ms. | 2 |
07/02/2014 | Correspondence of concurrence from the Ohio Historic Preservation Office electronically filed by Mrs. Kim D Carter on behalf of Wilson, Sean Mr. and Green, Steven Mr. and Leoni, Andrew Mr. and Melland, Kathleen Ms. | 2 |
06/30/2014 | Correspondence of Documentation of Completing required Conditions of Staff Report electronically filed by Mrs. Kim D. Carter on behalf of Wilson, Sean Mr. and Green, Steven Mr. and Leoni, Andrew Mr. and Melland, Kathleen Ms. | 3 |
06/09/2014 | Notice of construction starting on the South Central Power Company Blue Racer 138kV Transmission Line Project electronically filed by Mrs. Kim D Carter on behalf of Wilson, Sean Mr. and Green, Steven Mr. and Leoni, Andrew Mr. and Melland, Kathleen Ms. | 2 |
06/05/2014 | Correspondence Accepting Conditions in the Staff Report electronically filed by Mrs. Kim D Carter on behalf of Wilson, Sean Mr. and Green, Steven Mr. and Leoni, Andrew Mr. and Melland, Kathleen Ms. | 3 |
06/04/2014 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
05/27/2014 | Proof of Pub for the county of Monroe, South Central Power Company Blue Racer 138kV Transmission Line Project electronically filed by Mrs. Kim D. Carter on behalf of Wilson, Sean Mr. and Green, Steven Mr. and Leoni, Andrew Mr. and Melland, Kathleen Ms. | 4 |
05/22/2014 | Response Letter to expedited review extension electronically filed by Mrs. Kim D Carter on behalf of Wilson, Sean Mr. and Green, Steven Mr. and Leoni, Andrew Mr. and Melland, Kathleen Ms. | 2 |
05/05/2014 | Notice of payment in the Ohio Power Siting project - South Central Power Company Blue Racer 138kV Transmission Line Project. | 1 |
05/02/2014 | Letter of Notification South Central Power Company Blue Racer 138kV Transmission Line Project on behalf of Blue Racer Midstream, LLC Part 5 of 5 electronically filed by Mrs. Kim D Carter on behalf of Wilson, Sean Mr. and Green, Steven Mr. and Leoni, Andrew Mr. and Melland, Kathleen Ms. | 23 |
05/02/2014 | Letter of Notification South Central Power Company Blue Racer 138kV Transmission Line Project on behalf of Blue Racer Midstream, LLC Part 4 of 5 electronically filed by Mrs. Kim D Carter on behalf of Wilson, Sean Mr. and Green, Steven Mr. and Leoni, Andrew Mr. and Melland, Kathleen Ms. | 20 |
05/02/2014 | Letter of Notification South Central Power Company Blue Racer 138kV Transmission Line Project on behalf of Blue Racer Midstream, LLC Part 3 of 5 electronically filed by Mrs. Kim D Carter on behalf of Wilson, Sean Mr. and Green, Steven Mr. and Leoni, Andrew Mr. and Melland, Kathleen Ms. | 42 |
05/02/2014 | Letter of Notification South Central Power Company Blue Racer 138kV Transmission Line Project on behalf of Blue Racer Midstream, LLC Part 2 of 5 electronically filed by Mrs. Kim D. Carter on behalf of Wilson, Sean Mr. and Green, Steven Mr. and Leoni, Andrew Mr. and Melland, Kathleen Ms. | 48 |
05/02/2014 | In the matter of the Letter of Notification South Central Power Company Blue Racer 138kV Transmission Line Project on behalf of Blue Racer Midstream, LLC Part 1 of 5 electronically filed by Mrs. Kim D Carter on behalf of Wilson, Sean Mr. and Green, Steven Mr. and Leoni, Andrew Mr. and Melland, Kathleen Ms. | 24 |
|