Date Filed | Summary | Pages |
07/17/2015 | Notice of Withdrawal and Substitution of Counsel electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. | 3 |
06/18/2015 | Letter of Notification for Miller Switch-East Amsterdam 138 kV Transmission Line Rebuild Project electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. | 2 |
05/19/2015 | Letter of Notification -East Amsterdam Miller Switch 138 kV Transmission Line Rebuild Project electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. | 2 |
09/24/2014 | Correspondence accepting Staff-recommended Conditions of Certificate electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 2 |
09/18/2014 | Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB. | 6 |
09/12/2014 | Amended Application enclosing an addendum to the Application filed on June 27, 2014 (Part 6 of 6) electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 6 |
09/12/2014 | Amended Application enclosing an addendum to the Application filed on June 27, 2014 (Part 5 of 6) electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 7 |
09/12/2014 | Amended Application enclosing an addendum to the Application filed on June 27, 2014 (Part 4 of 6) electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 30 |
09/12/2014 | Amended Application enclosing an addendum to the Application filed on June 27, 2014 (Part 3 of 6) electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 26 |
09/12/2014 | Amended Application enclosing an addendum to the Application filed on June 27, 2014 (Part 2 of 6) electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 11 |
09/12/2014 | Amended Application enclosing an addendum to the Application filed on June 27, 2014 (Part 1 of 6) electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 19 |
07/14/2014 | Proof of Pub Miller Switch Project-East Amsterdam electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 5 |
06/27/2014 | Application continued for the East Amsterdam-Miller Switch 138 Kv Transmission Line Rebuild Project Part 4 of 4 electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 21 |
06/27/2014 | Application continued for the East Amsterdam-Miller Switch 138 Kv Transmission Line Rebuild Project Part 3 of 4 electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 13 |
06/27/2014 | Application continued for the East Amsterdam-Miller Switch 138 Kv Transmission Line Rebuild Project Part 2 of 4 electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 30 |