Date Filed | Summary | Pages |
02/24/2016 | Letter of Notification that the Inland-Jordan Q11 and Q14 138kV Transmission Line Loops to Clinic Hospital Substation Project was completed on October 13, 2014 filed by N. Bryksenkova on behalf of First Energy Service Company. | 1 |
09/30/2014 | Letter stating that the access for removing existing Structure #2638 and replacing it with a new structure was not feasible due to unanticipated field conditions for the Inland-Jordan Qll & Q14 138 kV Transmission Line Loops to CH Substation Project filed by J. Thacker on behalf of FirstEnergy Service Company. | 2 |
02/11/2014 | Letter serving as notice of an engineering design change for the Inland-Jordan
Q11 & Q14 138 kV Transmission Line Loops to CH Substation Project filed by J. Thacker on behalf of FirstEnergy Service Company. | 1 |
12/20/2013 | Response to the Letter of Notification on the
project filed on August 29, 2012 and approved November 2, 2012 filed by J.Thacker on behalf of FirstEnergy Service Company. | 1 |
10/25/2012 | Staff investigation report and recommendation filed on behalf of PUCO. | 1 |
08/29/2012 | Letter of notification of American Transmission Systems, Incorporated for the Inland-Jordan Q11 & Q14 138 kV Transmission Line
Loops to Clinic Hospital Substation Project. | 12 |
08/29/2012 | In the matter of the application of American Transmission Systems, Incorporated a Subsidiary of FirstEnergy Corp. letter of notification Inland-Jordan Q11 & Q14 138 kV transmission line loops to Clinic Hospital Substation. | 18 |