Date Filed | Summary | Pages |
03/20/2015 | Case Action Form to Close Cases effective 3/20/2015. | 6 |
01/17/2013 | Letter in response to the Construction Notice project filed on August 3, 2012 filed by Travis M. Turner on behalf of Energy Delivery Transmission and Substation Design FirstEnergy Service Company. | 1 |
11/19/2012 | Letter stating that construction for the Oregon Ditch project is expected to begin on approximately November 19, 2012 filed by T. Turner on behalf of FirstEnergy Service Company.
| 1 |
08/29/2012 | Staff Investigation Report and Recommendation filed by OPSB Staff. | 1 |
08/03/2012 | In the matter of the construction notice of American Transmission Systems, Incorporated for the Bayshore-Decant 138 kV Transmission Line Relocation for the Oregon Ditch Project. | 22 |