DIS - Case Record for 12-0891-EL-CSS Skip to main content

Case Record For:

12-0891-EL-CSS

Case Title: JACK TEUBNER VS OHIO EDISON/FIRST ENERGY
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: CSS-Complaint on service or safety
Date Opened: 3/8/2012
Date Closed: 1/24/2014
Printable Docket Card Service List
View All
1 - 15 of 18 documents 1 /  2 
Date FiledSummaryPages
01/24/2014Case action form closing case with an effective date of 1/24/14.1
01/24/2014Case action form to reopen case.1
12/04/2013Service Notice2
12/04/2013Entry ordering that in accordance with the above findings, Ohio Edison's July 17, 2013 motion to dismiss is granted; this complaint case is hereby dismissed and closed of record.3
11/13/2013Service Notice2
11/13/2013Attorney Examiner Entry cancels the hearing in this case which had been scheduled to occur on 12/04/2013. - electronically filed by Sandra Coffey on behalf of Daniel Fullin, Attorney Examiner, Public Utilities Commission of Ohio.2
07/17/2013Motion to dismiss for failure to prosecute and memorandum in support filed by Allison E. Headt on behalf of Ohio Edison Company (Respondent). 8
07/16/2013Notice of appearance of Lydia M. Floyd of the law firm Jones Day hereby as counsel for Respondent, Ohio Edison Company, filed by A. Haedt on behalf of Ohio Power Company.3
07/09/2013Service Notice1
07/09/2013Attorney Examiner Entry orders a hearing in this matter for 12/04/2013 at 11:00 a.m. in Hearing Room 11-A at the offices of the Commission located at 180 E. Broad St., 11th Flr, Columbus, Ohio. - electronically filed by Sandra Coffey on behalf of Daniel Fullin, Attorney Examiner, Public Utilities Commission of Ohio.3
06/14/2012Entry ordered, that the prehearing settlement conference previously scheduled for June 14, 2012 is rescheduled in accordance with finding (2). Finding (2) The attorney examiner finds that, by this entry, the prehearing settlement conference originally scheduled for June 14, 2012, at 10:00 a.m., at the offices of the Commission, is rescheduled to occur as a teleconference that will be conducted over the Commission's telephone bridge line on June 20, 2012, at 2:30 p.m. The parties are instructed to participate in the teleconference by calling the Commission's bridge line, namely 614-644-1099, at 2:30 p.m., on June 20, 2012. (DEF)2
06/14/2012Service Notice1
05/09/2012Service Notice1
05/09/2012Entry ordering that a settlement conference shall be scheduled for June 14, 2012, at 10:00 a.m., in Conference Room 1246, in the offices of the Commission, 12th, Floor, 180 East Broad Street, Columbus, Ohio 43215-3793. (DEF)3
03/29/2012Answer of respondent, Ohio Edison Company filed by A. Haedt.7
 
1 /  2 
      
      
Attorney General:
Attorney Examiner:
Fullin, Daniel