Date Filed | Summary | Pages |
03/20/2015 | Case Action Form to Close Cases effective 3/20/2015. | 6 |
05/10/2012 | Letter in response to the Letter of Notification on the project filed on July 18, 2011, be advised that construction on this project was completed on approximately May 4, 2012 filed by J. Thacker on behalf of FirstEnergy Service Company. | 1 |
09/22/2011 | Letter stating that the Hanna Substation Expansion project will begin on or shortly after October 4, 2011 filed by Jessica Thacker on behalf of FirstEnergy Service Company. | 1 |
08/23/2011 | Ohio Power Siting Board Staff investigation report and recommendation. | 1 |
07/19/2011 | In the matter of the application of American Transmission Systems Incorporated construction notice for the Hanna Substation Expansion project located at 4650 Sandy Lake Road in Rootstown Township, Portage County Ohio. | 17 |