03/13/2009 | Letter stating that the construction on the Yellowbush 138kV Line Extension Project was completed on or about March 12, 2009 filed by S. Nourse on behalf of Columbus Southern Power Company dba American Electric Power. (FAX) | 1 |
10/28/2008 | Notice stating that construction on the Yellowbush 138kV Line Extension Project will commence on or about November 3, 2008 filed by S. Nourse on behalf of American Electric Power. | 1 |
10/17/2008 | Staff investigation report and recommendation. | 1 |
09/15/2008 | Motion for waiver and memorandum in support filed by S. Nourse on behalf of the Ohio Power Company. | 2 |
09/09/2008 | In the matter of the letter of notification for the Yellowbush 138 kV extension service to Gatling Ohio LLC Mining Operations. | 19 |