Date Filed | Summary | Pages |
04/30/2009 | Notice of completion to the Ohio Power Siting Board for the work and installation of the Second Circuit on the Hayden - Roberts 345kV Line filed by M. Satterwhite on behalf of Columbus Southern Power Company. (FAX) | 1 |
03/20/2009 | Notice to the Ohio Power Siting Board that a construction company has been retained to install the Second Chance Circuit on the Hayden - Roberts 345kV line filed on behalf of Columbus Southern Power Company by S. Nourse. (FAX) | 1 |
03/13/2009 | Letter stating that construction on the Hayden-Roberts 345 kV Line Second Circuit Project was initiated on or about March 9, 2009 filed by S. Nourse on behalf of Columbus Southern Power Company dba American Electric Power. (FAX) | 1 |
08/29/2008 | Staff investigation report and recommendation filed. | 2 |
08/07/2008 | In the matter of the notice of Columbus Southern Power Company (American Electric Power) for the construction of Hayden-Roberts 345 kV line string second circuit. | 11 |