DIS - Case Record for 07-0715-EL-BTX Skip to main content

Case Record For:

07-0715-EL-BTX

Case Title: AEP-OHIO
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: BTX-Application for a Certificate/ Gas or Electric
Date Opened: 6/19/2007
Date Closed: 3/24/2015
Printable Docket Card Service List
View All
1 - 15 of 51 documents 1 /  4 
Date FiledSummaryPages
03/24/2015Memo closing case with an effective date of 3/24/15.1
03/01/2011Service Notice2
02/28/2011Entry ordered that CSP's motion for an extension of the protective order is granted for 36 months from the date the current protective order expires, that the Docketing Division maintain, under seal, the information filed on December 21, 2007, for a period of 36 months ending on February 14, 2014. 4
12/21/2010Motion for protective order, request for waiver and memorandum in support, filed by S. Nourse on behalf of American Electric Power Corporation. 4
12/23/2009Letter of Notification electronically filed by Mr. Matthew J Satterwhite on behalf of Ohio Power Company.2
08/14/2009Service Notice1
08/14/2009Entry granting CSP's motion for an extension of the protective order. (GS)2
06/19/2009Motion for protective order and memorandum in support filed by S. Nourse on behalf of American Electric Power Service Corporation.3
06/18/2009Motion for protective order and memorandum in support for extension filed on behalf of Columbus Southern Power Company by S. Nourse. (FAX)3
02/10/2009Response letter to Mr. Tommy Antill, Project Manager on behalf of the Ohio Power Siting Board filed by K. Lambeck. 1
01/26/2009Response letter to: Tommy Antill, Project Manager, on behalf of the Ohio Power Siting Board filed by K. Lambeck. 1
01/16/2009Response letter to: Tommy Antill filed on behalf of OPSB Staff, K. Lambeck.1
12/12/2008Letter to AEP regarding the commencement of construction on the Don Marquis 138kV Loop #1 Project filed by K. Lambeck, OPSB.1
11/04/2008Response letter sent to Mr. Antill filed by K. Lambeck.1
10/28/2008Notice stating that construction on the Don Marquis 138kV Loop #1 Project will be commenced on or about November 4, 2008, filed by S. Nourse on behalf of Columbus Southern Power Company dba American Electric Power.1
 
1 /  4 
      
      
Attorney General:
Lindgren, Thomas
McNamee, Thomas
Attorney Examiner:
See, Greta