Date Filed | Summary | Pages |
04/04/2007 | Letter notifying the Commission that the project was completed on March 7, 2007 filed by S. Lane on behalf of Duke Energy. | 1 |
03/23/2006 | Staff Investigation Report and Recommendation, filed by PUCO staff. | 1 |
03/01/2006 | Letter stating that the Phase 1 Archaeological Survey for the Cincinnati Gas and Electric Company's Maineville 138kV Transmission Line Loop has been submitted under separate cover, filed by S. Lane. | 1 |
02/17/2006 | In the matter of the Letter of Notification for Maineville 138 kv Electric Transmission Line, Loop regarding a Cincinnati Gas and Electric Company project. | 24 |
|