Date Filed | Summary | Pages |
10/12/2006 | Letter providing notice that the project was completed on September 14, 2006, on behalf of Columbus Southern Power Company dba American Electric Power, filed by S. Williams. | 1 |
04/05/2006 | Letter of notification on behalf of Columbus Southern Power Company, dba American Electric Power (AEP) filed by S. Williams. | 1 |
12/29/2005 | Staff Investigation Report and Recommendation filed by staff. | 2 |
11/21/2005 | In the matter of the application of the letter of notification for the proposed Harrison-Beatty 138kV line relocation for Meijer store in Grove City, Ohio | 28 |
|