Date Filed | Summary | Pages |
01/31/2006 | Memo stating that grade crossing improvements/upgrades ordered have been installed and are in service, and ordered case to be closed of record, filed on behalf of PUCO staff-Railroad Division. | 1 |
01/14/2005 | Service Notice | 2 |
01/12/2005 | Entry stating that the Commission's June 30, 2004 entry to CSX to complete the project is recinded; that CFE submit site plans and cost estimates for the project to the Commission and ORDC; approval of site plans and cost estimates by ORDC, CFE proceed with construction of the project with construction to be completed by January 12, 2006; ;CFE notify the Commission and ORDC 30 days before projected completion. | 3 |
01/05/2005 | In the matter of the authorization of the Central Railroad Company of Indianapolis dba Chicago, Ft. Wayne & Eastern to install an active grade crossing warning device in Allen County. | 3 |
|