09/17/2003 | Letter stating that construction on this project was completed June 28, 2003, filed on behalf of applicant by H. Loucks. | 1 |
06/19/2003 | Letter stating that construction on this project is scheduled to start on June 28, 2003 and the company will notify the Commission when construction has been completed, filed on behalf of applicant by H. Loucks. | 1 |
06/06/2003 | Letter to Mr. Loucks relative to project filing meets the informational requirements for a Construction Notice and project may proceed, and that the requested waiver of the 60 day filing time requirement is granted, filed on behalf of PUCO staff K. Lambeck, Chief. | 1 |
06/03/2003 | Investigation report approving the construction notice, filed by L. Winget, PUCO staff. | 5 |
05/28/2003 | In the matter of the Construction Notice of Columbus Southern Power Company for the Beatty-Canal/Beatty-McComb 138KV Line, relocate for Centex Homes, Inc. | 8 |
|