Date Filed | Summary | Pages |
10/27/2003 | Memo stating grade crossing improvements have been completed and placed in service and requesting closure of cases filed by G. Martin, PUCO. | 1 |
07/03/2003 | Letter to Mr. Tracy V. Drake, Executive Director of Columbiana County Port Authority from Susan J. Kirkland Manager, Safety Programs. | 8 |
06/16/2003 | Letter denying the allegations of the Commission's May 28, 2003 letter and demanding a show cause hearing, filed on behalf of Central Columbiana & Pennsylvania Railway by B. Gane. | 1 |
05/22/2003 | Entry ordered that the East Railroad Street project be added to this case. | 3 |
05/15/2003 | Subsidy agreement by the PUCO and Ohio Rail Development Commission, Central Columbiana & Pennsylvania Railway and Village of Columbiana. | 12 |
05/15/2003 | Memo requesting that the E.Railroad St. location crossing be added to the case of record, filed by G. Martin, PUCO staff. | 2 |
02/27/2003 | Additional information on behalf of applicant, by S. Kirkland. | 1 |
05/23/2002 | Service Notice. | 1 |
05/21/2002 | Entry ordering that Central Columbiana & Pennsylvania Railway submit to the Ohio Rail Development Commission site plans and cost estimates for the Pittsburgh Street Metz Road projects; that CC&P Railway file a letter in this docket advising the Commission that the site plans and cost estimates have been submitted to Ohio Rail Development Commission; that following approval of the site plans and cost estimates, CC&P Railway shall proceed with construction of the projects, to be completed by May 23, 2003. | 3 |
05/01/2002 | In the matter of the authorization of the Central Columbiana & Pennsylvania Railway (CCPA) to construct two active grade crossing warning grade crossing warning devices in Columbiana County. | 3 |