Date Filed | Summary | Pages |
05/09/2002 | Entry closing this case of record. | 2 |
03/21/2002 | Memo filed by G. Martin, PUCO staff, requesting that these cases be closed of record. | 1 |
09/19/2001 | Service Notice | 1 |
09/18/2001 | Memo filed by G. Martin, PUCO staff, with attached request from the Indiana & Ohio Rail System for a further extension of 30 days within which to complete the project. | 3 |
09/18/2001 | Entry ordering that I&O be granted its requested extension as delineated in Finding 4. (AE) | 1 |
08/17/2001 | Service Notice. | 1 |
08/16/2001 | Entry ordering that NS be granted the extensions as delineated in Finding 4; that the project should be completed by September 20, 2001. (AE) | 1 |
08/15/2001 | Memo recommending that NS be granted a 30-day extension of time, until September 20, 2001, within which to complete the active warning device projects, filed by L. Dalton, PUCO staff. | 1 |
07/20/2001 | Entry ordering that NS be granted extensions as delineated in Findings 4 and 5. (AE) | 2 |
07/19/2001 | Memo filed by L. Dalton, PUCO staff, stating that Norfolk Southern is requesting an extension of time in which to comply with the Commission order issued in this case (for Holmes County). | 2 |
07/19/2001 | Memo filed by L. Dalton, PUCO staff, stating that Norfolk Southern is requesting an extension of time in which to comply with the Commission order issued in this case (for Portage County). | 2 |
06/22/2001 | Service Notice | 1 |
06/21/2001 | Entry ordering that construction deadlines for the installation of active warning devices be extended to September 18, 2001 in Case No. 00-1038-RR-FED and January 17, 2002 in Case No. 00-1794-RR-STP. | 2 |
06/01/2001 | Memo, with attached request from Railroad, stating that the deadline for this project should be extended 60 days, filed on behalf of the PUCO staff by B. Johrendt. | 2 |
07/20/2000 |
Entry ordering that CSX, Indiana & Ohio, NOWR, and Norfolk Southern submit to the Commission site plans and cost estimates mates for the projects within 90 days of this entry; that CSX, Indiana & Ohio, NOWR, and Norfolk Southern proceed with construction of the projects, with construction to be completed by July 20, 2001; that CSX, Indiana & Ohio, NOWR, and Norfolk Southern notify the Commission's railroad section upon completion of each project, at which times Commission staff will make its final inspection. (4 pgs.)
| 4 |