Summary: |
Finding and order stating that by January 2, 2015, NS file notice that it has initiated with Duke, or any applicable utility, the process to ensure that electric service will be available at the involved grade crossing as set forth in finding (6); ordered that NS follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the project by September 3,2015. |
|