Summary: |
Finding and Order that by December 28, 2018 CSX filed notice that it has initiated with AEP or any applicable utility the process to ensure that electric service will be available at the involved grade crossing as set forth in Paragraph 8 and that CSX follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the project by November 28, 2019. |
|