Summary: |
Finding and ordered, That by May 4, 2018, CSX file notice that it has initiated with OEC, or any applicable utility, the process to ensure that electric service will be available at the involved grade crossings as set forth in Paragraph 8. It is, further, ordered, That CSX follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the projects by April 4, 2019. |
|