Summary: |
Entry ordering that by June 30, 2012, NS file a notice that it has initiated with Duke Energy, or any other applicable utility the process to ensure that electric service is available at the involved grade crossing; NS follow the detailed instructions outlined in the ORDC letter of construction to complete the project by February 25, 2013. |
|