Summary: |
ICN #0018 Letter stating that the expansion of the River- view Substation was completed on January 5, 1996, and interim rehabilitation will be completed by the end of January, 1996, and permanent rehabilitation of the dis- trubed areas, such as reseeding, will be completed in the Spring of 1996, filed on behalf of applicant by G. Jack. (1 pg.) |
|