Summary: |
Notice stating that two of the three crossing upgrades have been installed and the Georgesville Road/County Road 26 crossing upgrade has been substantially completed but due to the signal design for the crossing has taken longer than expected and as a result the April 30, 2009 construction deadline cannot be met filed on behalf of Camp Chase Industrial Railroad by K. Jameson. |
|