Summary: |
Finding and ordered, that, by March 15, 2012, NS file a notice that it has initiated with TE the process to ensure that electric service will be available at the involved grade crossing as set forth in finding 3; that NS follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the project by November 14, 2012. |
|